Lantz Corners sewer project is 30 percent complete

November 16, 2013

Photo by Ted Lutz – Construction is well underway for the sewage collection system in the Lantz Corners area of Hamlin Township. This is one of several construction sites along Route 6 between Lantz Corners and Mt. Jewett.

HAZEL HURST – Installation of sewer lines is well underway for the long-awaited Lantz Corners sewer district in the western end of Hamlin Township.
In a report to the township Board of Supervisors earlier this week, project engineer Dan Slagle said work on the sewage collection system is about 30 percent complete.