Dam project completion pushed back to 2019

April 16, 2014

Photo by Amy Cherry – Mike Rattay, East Branch Dam project manager, speaks to a small audience during the recent stakeholders meeting held at the East Branch Dam.

JONES TWP. – The completion date to the extensive East Branch Dam repair project has been pushed back to 2019, two years later than originally anticipated. The $280 million project entails constructing a full-length, full-depth concrete cutoff wall through the dam to reduce risk and restore the dam to normal operation.